Hi,
You can follow the below procedure,
1 Create a statistical order (an internal order used to evaluate costs for information purposes only) for each cost center in question.
2 In the order master data, enter the cost center to be monitored as the requesting cost center.
3 Activate availability control for the order. 4 During posting, post costs to the order instead of the cost center. The R/3 System treats these as statistical costs, and simultaneously makes (real) postings to the associated cost center. You can then use availability control for the order.
Hope this helps you and let me know if you have any doubts.
Regards,
Puri.