Hi,
There is a two Plan delivery time area in material master MM02 and inforecord ME1M, I was thinking we can select which one we will use with a simple setting on OMI8. Even I made this change and click scheduling info record system still takes plan delivery time from material master, am I doing right or there is another setting calculate PDT from inforecord ?